Creve Coeur Lake Memorial Bridge

A large double box girder cast-in-place segmental bridge constructed using a balanced cantilever method, this project provided many opportunities to explore the benefits of concrete maturity testing on a wide range of applications. The Con-Cure system was used to determine early-age in-place strength. Once sufficient strength had been reached, the contractor was allowed to begin[…]

AT&T Stadium, Dallas, TX

Precast and Prestressed Concrete Plant Operations Precast operations are often highly optimized already, but the use of concrete maturity reveals enormous savings in both time and costs that impress even the most advanced precaster. For example, one producer felt that they had optimized their mix design for thousands of risers for the new Dallas Cowboys[…]